Press Release: TCN Completes Reconstruction of Collapsed 132kV Towers, Restores Karu–Keffi–Akwanga Transmission Line

TCN Transmission News 

The Transmission Company of Nigeria (TCN) wishes to inform the public that it has completed the reconstruction of three collapsed 132kV transmission towers, T78, T79 and T80, and restored the Karu–Keffi–Akwanga Transmission Line.

The reconstruction was completed at 5:31pm on Wednesday, 28 October 2026, restoring the transmission pathway serving the 132/33kV Keffi and Akwanga Transmission Stations.

The towers had collapsed on 7 October 2026 following heavy rainfall and strong winds. TCN's maintenance crew worked diligently to reconstruct them and restore the affected line.

TCN remains committed to maintaining and strengthening its transmission infrastructure to ensure the reliable and efficient transmission of bulk electricity across the country.


Signed

Management

Transmission Company of Nigeria (TCN)

28/10/26