The Transmission Company of Nigeria has successfully energized a new 63MVA, 132/33kV power transformer at the Jebba Transmission Substation, Niger State on Saturday, 11th May, 2024.
The commissioned transformer has increased the Substation’s capacity by 50MW making available more bulk power for Ibadan Electricity Distribution Company (IBEDC), to distribute to it’s customers in parts of Niger and Kwara State.
The transformer is part of the projects executed under the Presidential Power Initiative (PPI) programme.