TCN Energizes Two Power Transformers In New Haven Substation


The Transmission Company of Nigeria (TCN) has energized two newly installed power transformers in its New Haven Transmission Substation in Enugu.


The transformers comprising one 150MVA and one 100MVA  power transformer were energized on the 8th and 9th of November, 2024, respectively. 



The new transformers have significantly increased the substation’s wheeling capacity by 120MW on the 330kV level and 80MW on 132kV level. 


The transformers will enable TCN wheel more bulk electricity to distribution load centres of  Enugu Electricity Distribution Company (EEDC) for off-take to its customers in Enugu, Ebonyi and parts of Benue State.