In continued pursuit of its rehabilitation and expansion programme, the Transmission Company of Nigeria (TCN) commissioned a new 100MVA power transformer in its 132/33kV Ilorin Transmission Substation in Kwara State.
The new transformer, which was commissioned on March 25, 2024, added 80MW to the substation's capacity. Ibadan and Benin DisCos can now take more power for onward distribution to electricity consumers within Ilorin metropolis and environs.
The transformer was procured under the TCN-World Bank power project.