Press Release: Ongoing Rehabilitation Works at Amuwo 132/33kV Transmission Substation

 

The Transmission Company of Nigeria (TCN) wishes to inform the public that rehabilitation works at the Amuwo 132/33kV Transmission Substation, being executed by its contractor, are progressing steadily. The project, which commenced in March this year, remains on track for completion in July 2026 as earlier announced.


Currently, Gas Insulated Switchgear (GIS) equipment is being installed, and two 60MVA power transformers have been delivered to replace the existing 30MVA units. Upon completion, the substation’s capacity will increase by an additional 60MVA, significantly enhancing power transmission capability.

To mitigate the impact of the works, TCN earlier deployed two mobile transformers to enable Eko and Ikeja Electricity Distribution Companies to continue offtake for their customers, preventing a total blackout during the rehabilitation period.

This major overhaul will increase the substation's capability and eliminate the frequent breakdowns and downtime experienced with the old GIS. Meanwhile, TCN is mindful of the inconvenience to electricity customers and is doing all it can to ensure timely completion of the project.

We appeal to affected electricity consumers to bear with us, as the ongoing works are aimed at increasing the Amuwo Substation’s capacity to deliver long-term benefits for affected customers.

We reaffirm our commitment to the continued expansion of transmission capacity nationwide to meet the growing demand for bulk electricity.


Ndidi Mbah
GM, Public Affairs  
4/5/26



Previous Post Next Post