The Transmission Company of Nigeria, (TCN) has restored power on the Benin-Omotosho 330kV Transmission Line at 7:05 pm on Thursday, 2nd July, 2026.
The restoration followed an outage on the line on 25th June, 2026, caused by detachment of conductors. TCN engineers have since worked to restring and complete maintenance on the affected sections of the transmission line.
With the line now back in service, the Benin Electricity Distribution Company (BEDC), Eko Electricity Distribution Plc (Eko DisCo) and Ikeja Electric will be able to off-take more power for supply their customers in their franchise areas.
TCN apologises for the inconvenience caused by the outage and appreciates the understanding and cooperation of all affected during the period.
Ndidi Mbah
GM, Public Affairs