TCN Transmission News
The Transmission Company of Nigeria (TCN) wishes to inform the public that a scheduled annual preventive maintenance will be carried out at its Effurun 132/33kV Transmission Substation on Wednesday and Thursday, October 28th and 29th, 2026, from 10:00am to 3:00pm daily.
This work is necessary to enable EPC Contractors safely commission the SERGI fire protection system on the 100MVA 132/33kV Transformer (T2) 3EFRTR2.
Consequently, Benin Electricity Distribution Company (BEDC) 33kV feeders, including Refinery 1 & 2, Effurun, PSLM, and Warri, will experience a brief power interruption of approximately 20 minutes to allow TCN engineers carry out essential switching operations.
TCN apologises for any inconvenience this may cause electricity customers within the affected areas.
Signed
Management
Transmission Company of Nigeria, TCN
27/10/26
